Project: Woodstock Warehouse Building
Construction Management Work Commissioned in: August 2024
Address: 352 Griffin Way, Woodstock, Ontario
Amenities: 1-storey warehouse building with 9 potential units
Status: Phase-1 is 85% complete, and Phase-2 is 30% complete as of May 2026
In 2024, n Construction Inc. was commissioned to provide construction management services for a proposed warehouse development in Woodstock, Ontario, with a total gross floor area of 108,927 square feet. Construction activities have continued to advance steadily across both phases of the project, with significant progress achieved to date.
Progress of Work: For Phase 1, the building envelope and roof construction have been completed. HVAC, electrical, and sprinkler installations are currently underway, while interior fit-out work is scheduled to commence in the upcoming phase of construction. Retaining wall installation for the loading bay area is in progress.
For Phase 2, the footings and slab-on-grade have been completed, along with the perimeter wall construction. Structural steel installation has commenced and is anticipated to be completed by mid-June. Retaining wall construction for the loading bay area is also ongoing.